After 8 months of a construction work on the new Silesia City Center (SCC), the Erbud prime contractor is concluding the fourth stage of works. Raw state of the oval central part of the building is almost finished. The frame construction is 6,5 meters high at present. It ...

Construction works on the new part of Silesia City Center (SCC) started 7 moths ago. Today, a raw skeleton of characteristic oval elevation of the extended part finally can be seen. The new building will be finished in autumn 2011. According to the project manager of the extension, DIL ...

In autumn 2011, Silesia City Center (SCC), the biggest entertainment and shopping center in the region will be able to offer additional 20 000 sq. meters of retail space in 60 new shops. At present, construction works on the extension of the Center passes the halfway mark. Currently, SCC has ...

Construction works on the new part of Silesia City Center began six months ago and are to passed the halfway mark. It is planned to finish the new building in 13 months. At present, a fourth stage of works is in progress. This stage will be finished in spring. A ...

Three tower cranes, carrying about 140 tons of construction materials daily, a 87 000 cubic meters excavation site, more than 5 000 cubic meters of soil being removed every day, 310 workers – these are present numbers concerning the extension of Silesia City Center. Since the beginning of January, the ...

Ten months left to finish construction works on new Silesia City Center (SCC). To be on time with the schedule, works are progressing simultaneously in several sections of the construction site. An excavation site covers 87 000 cubic meters. At present, construction crews demolish a west-south part of existing SCC ...

Construction works on new Silesia City Center (SCC) have entered the fourth phase. It is the longest stage of the works and will be conducting until the end of February 2011. At present, Erbud’s crews are working on the foundations, underground car park and a cavity wall ...

The new part of Silesia City Center (SCC), which will be delivered in autumn 2011, has already attracted ten tenants. Three lease agreements were signed last week. The new tenants are Van Graaf with its store covering 4 000 sq. meters and two brands of Ultimate Fashion – River ...

Construction works on new Silesia City Center (SCC) entered the third phase of six planned. Builders are currently working on foundations for an underground car park which will be able to hold about 900 vehicles. Together with the existing parking lot, it will be the biggest underground car park ...

The extension of Silesia City Center (SCC) attracts new brands to the shopping complex and to the Upper Silesia region. About 60 new retail units will be opened in new SCC. Among first tenants are brands which have not been available in the region before. These are, among others, ...