Last Saturday, the Railway Station’s platform number 1 being under redevelopment since October 2010, was delivered and opened for travelers. Next to be refurbished is the platform number 2 which is already out of use. The platforms number 3 and 4 are still operating and will be revamped respectively ...

Works on the new Railway Station and Galeria Katowicka are to be entered into a next stage – construction of bearing pillars and ceilings. To make the works more efficient the first tower crane was installed at the site last week. There will be seven more such cranes. Meanwhile, ...

PKP Polish Railway Lines S.A. (PKP PLK), a company of PKP Group responsible for management of national railway network, chose a prime contractor which will redevelop platforms number 2, 3, 4* and surrounding infrastructure of Katowice Railway Station. The contract exceeding net ...

Works are in full swing at the construction site of the new Railway Station and Galeria Katowicka. A few weeks ago, the ground for foundation of Galeria Katowicka was started to be stabilized with lean concrete. Tonight, a first part of the foundation slab was poured with concrete. The ...

For the past few months, the Railway Station located in the very heart of Katowice has been undergoing a reconstruction process carried out by Neinver and PKP S.A. One of the biggest infrastructural investments in Poland is already complete when it comes to the demolition stage and a diaphragm ...

In June, construction crews of the new Railway Station and Galeria Katowicka concluded all demolishment work on the former Station’s building including its structure, foundation and an adjacent infrastructure. This week, a concrete sleeper of the foundation plate was started to be laid in the central part of ...

Neinver Polska, a developer of the new Railway Station and Galeria Katowicka, prepared a film which is dedicated to the construction aspects of the investment. Viewers are guided by representatives of the project’s prime contractor, the Strabag company, and SUD Architectes – designers of the complex. ...

A cornerstone has been laid for the integrated transportation, retail and office center that is being developed by Neinver and Polish State Railways (PKP S.A.) at Szewczyka Sq. in Katowice. The ceremony, which saw the participation of a couple hundred guests, took place at the construction site, where a ...

Since the morning, citizens of Katowice and visitors can scan their handprints at Szewczyka Square – the construction site of the new Railway Station and Galeria Katowicka. This way, everyone can “bear a hand” in building the new complex symbolically. All the handprints saved on a hard disc ...

Next Friday, on 27th of May, an event called “Bear a hand in building the new center of Katowice” will take place at Szewczyka Square. On the occasion of a cornerstone ceremony planned for 31st of May, citizens will have a chance to bear its hands symbolically in building the ...