Cultural district one-third done

August 7, 2013 Katowice the City 0

The commissioning process and performance testing in relation to the works on the new seat of Silesian Museum was ended. In general, the building is now completed and only the troubleshooting will take place inside. Construction works on the remaining two other facilities of the cultural district are still underway.

During the last 56 days the commissioning committee were checking that the performance of the total building

No Image

Cultural district takes shapes

May 31, 2013 Katowice the City 1

The new cultural district in Katowice consists of three buildings which are now at different stages of development – while works on the Silesian Museum’s seat are to be concluded in a few days, the construction of the International Convention Center will be relaunched after several months of suspension.

According to the contract, Budimex is going to finish the works on the Silesian Museum next week