No Image

Oval elevation of new SCC emerges

March 29, 2011 Katowice the City 0

Construction works on the new part of Silesia City Center (SCC) started 7 moths ago. Today, a raw skeleton of characteristic oval elevation of the extended part finally can be seen. The new building will be finished in autumn 2011.

According to the project manager of the extension, DIL Polska Baumanagement, the semicircled elevation should be concluded in summer. It will be made of glass, aluminium and ceramic elements forming an open-work “screen”.

No Image

New SCC construction nears halfway point

February 17, 2011 Katowice the City 0

Construction works on the new part of Silesia City Center began six months ago and are to passed the halfway mark. It is planned to finish the new building in 13 months.

At present, a fourth stage of works is in progress. This stage will be finished in spring. A celling of an underground car park for more than 500 vehicles is going to be concluded by the end of march. At the same time, construction crews works on a celling of the “0” level.

No Image

Works on foundations of new SCC

November 10, 2010 Katowice the City 0

Construction works on new Silesia City Center (SCC) entered the third phase of six planned. Builders are currently working on foundations for an underground car park which will be able to hold about 900 vehicles. Together with the existing parking lot, it will be the biggest underground car park in Katowice comprising 1 700 places.

At present, up to 5 000 cubic meters of soil are transported out of the construction site each day.