Budus is to build a passive building

July 25, 2011 Katowice the City 0

Today, on 25th of July, representatives of the Science and Technology Park of Euro-Centrum signed a contract with the Budus S.A. building company, which will raise a passive building – the new seat of the Park. Also it is designed for new technologies’ companies.

Budus S.A. had tendered for the contract together with eight other companies, however only three firms decided to make final bids. Price proposed by Budus was the lowest and amounts PLN 37 million.

No Image

Fast pace of work on Konduktorska St.

April 26, 2011 Katowice the City 0

Builders of the first office building of the Upper Silesian Industrial Park (GPP) set the hectic pace for construction work. Late February, Budus SA – a prime contractor of the project – was finishing a first storey of the building. Now, construction of a sixth storey is under way. Then, there will be only one more floor left to reach the final height of seven storeys.

The building will offer all necessary amenities to its tenants as suspended ceilings, lifted floors,

No Image

Construction works at 39 Konduktorska St.

February 28, 2011 Katowice the City 0

Construction works on the first building of office park located in the area of the Upper Silesian Industrial Park (GPP) were started in December last year. Recently, a construction crew erected first two levels and the building is raising. Already two tower cranes work at the construction site.

The building is supposed to be ready in the turn of 2011 and 2012. It will cover approximately 7 500 sq. meters of office space for rent.

No Image

Works on first office building of GPP launched

January 18, 2011 Katowice the City 0

The Upper Silesian Industrial Park (Górnośląski Park Przemysłowy, GPP) commenced construction works on its first of four buildings planned within the office park at 39 Konduktorska St. in Katowice. Budus S.A. was chosen as the prime contractor of the project.

“The groundbreaking took place last month, in December 2010. Currently, earthworks are underway for the building’s foundations. The construction works will take 12 months”