First works on concrete foundation

In June, construction crews of the new Railway Station and Galeria Katowicka concluded all demolishment work on the former Station’s building including its structure, foundation and an adjacent infrastructure. This week, a concrete sleeper of the foundation plate was started to be laid in the central part of Szewczyka Sq. Meanwhile, works on removing 365 000 cubic meters of soil from the construction site are being continued. The excavation will hold a two-storey underground car park, Galeria Katowicka’s -1 floor, underground bus station and a section of Dworcowa St. The builders also continue to anchor the 870-meters long diaphragm wall.